A A alone can do 1/4th of the work in 2 days. B alone can do 2/3rd of the work in 4 days. If all the three work together, they can complete it in 3 days so what part of the work will be completed by C in 2 days ? August 18, 2021 1 Min Read 0 264 August 18, 2021 1 Min Read 0 264 Answer : A. 1/12 Time and Work Editor Continue Reading