T The ratio of efficiency of A is to C is 5:3. The ratio of no.of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C left the work after 2 days. The no of days taken by A to finish the remaining work ? August 18, 2021 1 Min Read 0 32 August 18, 2021 1 Min Read 0 32 Answer : C. 6 Time and Work Editor Continue Reading
B Babla alone can do a piece of work in 10 days ashu alone can do it in 15 days. The total wages for the work in Rs.5000. How much should babla be paid of they work together for entire duration of the work ? August 18, 2021 1 Min Read 0 896 August 18, 2021 1 Min Read 0 896 Answer : B. 3000 Time and Work Editor Continue Reading