A train speed past a pole in 15 seconds and a platform 100 m long in 25 seconds. Its length is ?
A. 50 m
B. 150 m
C. 200 m
D. None of these
Answer : B. 150 m
Explanation :
Let the length of the train be x metres and its speed by y m/sec.
Then, x / y = 15
=> y = x / 15
(x + 100) / 25 = x / 15
=> 15(x + 100) = 25x
=> 15x + 1500 = 25x
=> 1500 = 10x
=> x = 150 m.
Categorized in:
Tagged in:
a 600 meter long train crosses a signal post in 40 seconds, a train 120 m long crosses a pole in 10 seconds, a train 125 m long passes a man, a train crosses a pole in 10 seconds, a train crosses a pole in 15 seconds, a train crosses a post in 15 seconds and a platform 100 m long in 25 seconds. its length is, a train moves past a telegraph post, a train moves past a telegraph posta train running at the speed of 60 km/hr crosses a pole in 9 seconds. find the length of the train, a train of 100 meters long takes 6 seconds, a train running at the speed of 60 km/hr crosses a pole in 9 seconds. find the length of the train, a train runs past a telegraph post, a train takes 10 seconds to cross a signal post, a train takes 18 seconds to pass completely, adani enterpris interview questions and answers, adani green energy ltd interview questions and answers, adani ports ltd interview questions and answers, adani total gas ltd interview questions and answers, adani transmission ltd interview questions and answers, ambuja cements interview questions and answers, apollo hospital interview questions and answers, aurobindo pharm interview questions and answers, avenue supermarts ltd interview questions and answers, axis bank interview questions and answers, bajaj auto interview questions and answers, bajaj finance interview questions and answers, bajaj finserv ltd interview questions and answers, balkrishna industries interview questions and answers, bandhan bank interview questions and answers, berger paints interview questions and answers, Bharat Petroleum Corporation Ltd interview questions and answers, biocon interview questions and answers, britannia industries ltd interview questions and answers, cadila health interview questions and answers, coal india Ltd interview questions and answers, colgate interview questions and answers, CTS interview questions and answers, dabur india ltd interview questions and answers, determine the speed of a train of length 240 meters if it crosses a pole in 15 seconds, divis labs interview questions and answers, dlf interview questions and answers, Dr. Reddys Labs interview questions and answers, eicher motors ltd interview questions and answers, gail (India) Ltd interview questions and answers, gland pharma ltd interview questions and answers, godrej consumer products ltd interview questions and answers, godrej properties interview questions and answers, grasim Industries ltd interview questions and answers, gujarat gas ltd interview questions and answers, havells india ltd interview questions and answers, hdfc life insurance company ltd interview questions and answers, hero motocorp interview questions and answers, hindalco industries ltd interview questions and answers, Hindustan Unilever Ltd interview questions and answers, hindustan zinc ltd interview questions and answers, how many seconds will a 500 meter, ICICI Lombard interview questions and answers, icici prudential Life Insurance interview questions and answers, Indian Oil Corporation Ltd interview questions and answers, indus towers ltd interview questions and answers, indusind bank interview questions and answers, interglobe aviation interview questions and answers, jsw steel interview questions and answers, jubilant foodworks ltd interview questions and answers, kotak mahindra bank interview questions and answers, L&T Infotech interview questions and answers, larsen & toubro Ltd interview questions and answers, Lupin interview questions and answers, m&m interview questions and answers, marico interview questions and answers, maruti suzuki interview questions and answers, motherson sumi systems interview questions and answers, muthoot finance hdfc amc interview questions and answers, Nestle interview questions and answers, nmdc ltd interview questions and answers, ntpc ltd interview questions and answers, Oil and Natural Gas Corporation (ONGC) interview questions and answers, pi industries ltd interview questions and answers, pidilite industries interview questions and answers, power grid corporation of India interview questions and answers, problems on trains with explanation, ril partly paid interview questions and answers, Sapient Nitro Interview, sbi card interview questions and answers, sbi life insura interview questions and answers, shree cements ltd interview questions and answers, siemens interview questions and answers, speed of a goods train is 72 km/hr, srf limited interview questions and answers, state bank of India (SBI) interview questions and answers, Steel Authority of India Ltd (SAIL) interview questions and answers, sun pharma interview questions and answers, tata consumer products ltd interview questions and answers, tata motors interview questions and answers, tata steel interview questions and answers, titan company interview questions and answers, torrent pharma interview questions and answers, train a crosses a pole in 25 seconds, two trains of length 125m and 175m, two trains running in opposite direction cross each other, ultratech cement interview questions and answers, United Phosphorus Ltd (UPL) interview questions and answers, united spirits interview questions and answers, vedanta ltd interview questions and answers, Wipro Interview Questions for Freshers | Wipro Fresher Interview Questions, Zoho Interview Questions and Answers, zomato interview questions and answers